Development Builds System TAIM_442 Time Line Report Sun 11 Feb 2024 - Sun 04 Feb 2024

TAIM_442 Time Line Sun 11 Feb 2024 - Sun 04 Feb 2024 [NB: most recent events first]
previous week · next week

Thu 08 Feb 2024 08:50:02pm Package 36019 pushed to review
08:45:09pm Conveyor created new package 36064 - TAIM_442_36064
08:45:08pm Conveyor closed package 36019 - TAIM_442_36019
08:37:59pm Build TAIM 4.42-Babel-Infrastructure upload completed - /TAIM_4.42-Babel_4.42.003-57-Infrastructure
08:37:55pm Build TAIM 4.42-Babel-Infrastructure upload started - /TAIM_4.42-Babel_4.42.003-57-Infrastructure
08:37:54pm Build TAIM 4.42-Babel upload completed - /TAIM_4.42-Babel_4.42.003-57
08:37:18pm Build TAIM 4.42-Babel upload started - /TAIM_4.42-Babel_4.42.003-57
08:37:14pm Build TAIM 4.42-Babel upload started - /TAIM_4.42-Babel_4.42.003-57