Development Builds System Receiver_564_624 Time Line Report Mon 04 Sep 2023 - Mon 28 Aug 2023

Receiver_564_624 Time Line Mon 04 Sep 2023 - Mon 28 Aug 2023 [NB: most recent events first]
previous week · next week

Thu 31 Aug 2023 12:11:40pm Build DeviceOptions-Rx-5.63 upload completed - /DeviceOptions-Rx-5.63-Build.12
12:05:30pm Build DeviceOptions-Rx-5.63 upload started - /DeviceOptions-Rx-5.63-Build.12
11:33:29am Build DeviceOptions-Rx-5.63 upload completed - /DeviceOptions-Rx-5.63-Build.11
11:27:13am Build DeviceOptions-Rx-5.63 upload started - /DeviceOptions-Rx-5.63-Build.11