Development Builds System Focus50_Avocet Time Line Report Mon 04 Oct 2021 - Mon 27 Sep 2021

Focus50_Avocet Time Line Mon 04 Oct 2021 - Mon 27 Sep 2021 [NB: most recent events first]
previous week · next week

Thu 30 Sep 2021 12:01:36am Package 27493 pushed to review
Wed 29 Sep 2021 11:13:23pm Conveyor closed package 27493 - Focus50_Avocet_27493
11:11:49pm Conveyor created new package 27550 - Focus50_Avocet_27550
11:01:46pm Build TSCommunicationTools upload completed - /TSCommunicationTools_4.8.190
11:01:13pm Build TSCommunicationTools upload started - /TSCommunicationTools_4.8.190